Before the walkout began Sept. 6, Boeing expected to deliver 119 planes in the three months ending Sept. 30, spokesman Todd Blecher said.
Blecher attributed about 30 of the non-deliveries to the strike by the International Association of Machinists and Aerospace Workers, which represents about 25,000 electricians, riveters, forklift operators and other hourly workers in and around Seattle, 1,500 in Gresham, Ore., and 750 in Wichita, Kan.
Key issues in the dispute include pay, medical coverage, retirement benefits and job security.
A handful of aircraft, all 777s except for one 767, were not delivered as expected in the third quarter because of continuing problems with a galley supplier, Blecher said. "The supplier still has to catch up," he said.
Boeing's Web site showed, and Blecher confirmed, that 10 planes were delivered between Sept. 6 and Sept. 30- more than three times the three planes that were delivered during a 24-day Machinists union strike in 2005. Boeing failed to deliver more than two dozen planes on schedule during the earlier strike.
"That's just a function of how many airplanes were out there all finished and waiting either for certification or for a customer to come and get them," he said.
During the same period Boeing logged orders for 37 planes, including 9 767-300ERs by All Nippon Airways and 24 planes by unidentified buyers.
Boeing officials have said the company stopped assembling aircraft after the strike began.
"Obviously, our members are having an impact on Boeing's bottom line and the production lines," said Connie Kelliher, a spokeswoman for the Machinists. "They need our members to get back to building airplanes."