| While concern over the prison 
            exceeding their flow limits became a problem in July, daily 
            communications and collaboration have brought them back into line 
            with set standards. Still, the general flow through the plant 
            exceeds capacity on a regular basis. Bob Merreighn, facility 
            operator and lab technician, pointed out on the daily reports that 
            after a week without rain the flow through the plant was between 
            3.4 and 3.6 million gallons per day. Expanded capacity and 
            newer, more stringent controls on wastewater treatment prompted the 
            need for the upgrade. The facility operation permit comes up for 
            renewal this fall. Operators began working on plans about a year and 
            a half ago in order to meet IEPA requirements for renewal.   
      
       The IEPA approved a 
            20-year revolving loan at 2.6 percent interest to fund the project. 
            The IEPA is also the final authority to approve the construction 
            plans. The city has chosen to work under a design-build project, 
            using a single source for design and implementation. Environmental 
            Management Corporation contracts with other firms, including an 
            engineering firm, Donahue and Associates, and a construction firm, 
            Paric Corporation. The original facility 
            was built at this site in 1936. The designers foresaw the need for 
            expansion in the future and incorporated space in the original 
            plans.  The current design of 
            the facility, last updated in 1978, provides for wastewater to be 
            treated by two separate methods.   
      
       Wastewater enters the 
            plant at two locations. One-third of Lincoln wastewater enters via 
            the Sherman Street tile and proceeds to the "new plant," receiving 
            aerobic treatment. The other two-thirds enters the facility via "the 
            old building." Before this water reaches the aerobic treatment, it 
            first passes through a progression of settling and filtering 
            processes.  Initially this 
            wastewater passes through a bar screen to remove large solids. These 
            solids are removed from the screen to a large dumpster, emptied once 
            weekly by area disposal services. The wastewater passes on to the 
            primary settling tanks. Sludge settles to the bottom, and 
            free-flowing water moves on to the next stage. In this stage 80 
            percent of the solids that can be removed from the water are 
            separated.  The sludge from the 
            settling tanks moves directly on to the digesters, while the water 
            from the settling tanks runs to the trickling filters. The 
            wastewater is sprayed over large, open tanks by long, rotating arms. 
            It trickles down through softball-sized rocks to the bottom of the 
            filter. Bacteria and algae living on the rocks break down chemical 
            compounds such as ammonia present in the water.  In the next stage, 
            water sits in a clarifier. As in the settling tanks, sludge sinks to 
            the bottom of the clarifier. The clarifier also has slow-moving 
            skimmers to remove scum from the surface of the water. Water from 
            this stage slowly spills over a ledge and moves on by gravity to the 
            aerators in the "new plant."   
             [Photos by Jan Youngquist]
 [A slow-moving skimmer takes scum off the top 
            as water pours over the edge in the clarifier.]
   
            [to top of second column in
this article]
             |  
         The facility 
            currently has seven aeration tanks. In these seven large tanks, 
            blowers located on the bottom of each tank churn the wastewater. The 
            churning mixes oxygen down into the wastewater and suspends sludge 
            in the water. Wastewater during this segment usually has a dark 
            brown color. In Lincoln, though, wastewater moving through the 
            aerators looks black. Black coloring would normally indicate a 
            serious problem with the treatment process; however, the black 
            coloring is explained away by the inks contained in wastewater 
            coming from Willamette Industries (Weyerhaeuser).   
             [In the aeration tanks, blowers along the bottom 
            churn the wastewater, black from the ink used at Weyerhaeuser.]
 This wastewater is 
            pumped into a final clarifier. The water that comes out of this 
            clarifier is injected with chlorine. The chlorinated water spends 35 
            minutes flowing down the Parshall Flume before emptying into Salt 
            Creek. During the water’s passage, the chlorine is neutralized by 
            compounds in the water. No free chlorine empties into the creek. 
            Drops along the flume further aerate the water. All sludge during the 
            treatment processes goes to the digesters. Two digesters work to 
            make the sludge as thick as possible. The thickened sludge is then 
            pumped into concrete beds for drying. The dried sludge is then 
            hauled away by farmers and spread on fields as fertilizer. The 
            treatment facility splits the cost of transporting the dried sludge 
            with the haulers. In addition to more 
            office space and a new maintenance building, plans for the upgrade 
            include the addition of a clarifier. Two clarifiers are currently 
            installed, and space for two more was left by the original 
            designers. Also in the plans, the two trickling filters will be 
            converted to more modern filters.    
             [A swinging arm spreads wastewater over algae and 
            bacteria-covered rocks in the trickling filters. The trickling 
            filters will be converted into a more modern treatment system in the 
            upgrade.]
 Five aeration tanks 
            will be added at the end of the seven existing ones, extending the 
            complex of tanks 100 feet. The addition of more aeration tanks 
            increases detention time — time for pollutants to be released from 
            the water. Currently, water is detained in the tanks for about six 
            hours. Ideally, water would be detained for eight to 10 hours. The 
            addition also increases the capacity of the system, improving 
            performance overall.  An old vacuator, 
            which has not been used for many years, will be removed. The 
            vacuator was once needed to remove grease and other pollutants in 
            the wastewater from a chicken processing plant in the area. Storage 
            bins located on the southern side of the facility will also be 
            removed. New IEPA standards call for the removal of such bins due to 
            the possibility of leakage.  The construction is expected to last a 
            little over one year. Wastewater facilities typically require an 
            upgrade about every 20 years but are subject to changes in IEPA 
            regulations every few years when facilities must renew their 
            permits. [Trisha
          Youngquist]   
       |