Although it meant leaving his family in Tokyo, Kakuta had jumped at the chance for a public affairs job with TEPCO in Fukushima three years ago. He had always admired the company's teamwork and looked forward to a new challenge. He got the biggest of his life. ___ By late afternoon, Unit 1 was spiraling out of control, with its power and cooling systems down. The heat from decaying radioactive elements in the fuel rods was growing. As the core overheated, it burned off its coolant water, exposing the 13-foot (4-meter) rods. In turn, steam from the evaporated water was building up inside the containment chamber. As the heat and pressure rose, the uranium pellets inside the rods melted through their zirconium casings. When the zirconium reached 2,200 degrees Fahrenheit (1,200 Celsius), it reacted with the water, producing hydrogen. This was obviously going to get worse before it got better. Yukio Edano, the chief Cabinet spokesman, is the face of Japan's government. At 7:45 p.m., his job was to make an unprecedented statement to the nation
-- but make it sound routine and reassuring. "We have declared a nuclear emergency," he said from behind a podium in the press conference room at the prime minister's office. "Let me repeat that there is no radiation leak, nor will there be a leak." He was wrong. Recently released TEPCO documents reveal that radiation was detected at the plant perimeter at 5:30 p.m., but the utility apparently didn't fax those readings to the government until shortly after 9 p.m. In the meantime, a two-mile (three-kilometer) evacuation zone around the plant was established. That later would become 6 miles (10 kilometers), then 12 (20). In the end, more than 80,000 people would be forced to flee. Fukushima Dai-ichi's operators, meanwhile, were faced with a twofold response: Vent and flood. Venting to release pressure and prevent an explosion, flooding to keep things cool. But venting would release radioactivity into the air. And flooding with seawater would ruin the equipment because of the salt. Around 9 p.m., less than six hours after the tsunami, officials at the prime minister's office started to press TEPCO to vent. TEPCO hesitated. Fukushima Dai-ichi was the utility's golden goose. Designed primarily by General Electric, it went online in 1971 and had kept the lights shining in Tokyo ever since. Unlike newer facilities, it was paid for, and it was generating profits with each megawatt it produced. TEPCO knew that venting radioactivity would cast doubt on the safety of the nuclear industry around the nation, and the world. But the options were dwindling. The outage of primary and backup power -- a scenario that exceeded planners' precautions
-- was severely hampering operations. The first emergency power vehicle sent by TEPCO got stuck in the chaotic post-tsunami traffic. A backup truck from another power company arrived at 11 p.m., but the cable it brought was too short to hook up. At 3:05 a.m., Trade and Industry Minister Banri Kaieda trotted out TEPCO executive Akio Komori for a public announcement of the plan to vent the Unit 1 containment vessel. Seven minutes later, Edano took to the podium, this time to warn the public that the action would entail the release of radioactive isotopes. Again, he urged calm. For those who knew what was happening, the urgency was mounting. The containment chamber around the core was bulging with pressure twice as high as its maximum operational limit and nearly matching the company's required venting standard. "We kept telling TEPCO to do it quickly, asking how come it wasn't happening," Edano recalled later. Nearly four hours after the initial announcement, an exasperated Kaieda ordered TEPCO to vent. It was 6:50 a.m.
Surging radiation forced workers to abort their attempt to open the valves manually. Then they tried to open them remotely and repeatedly failed, probably because of the power outage but possibly also a design flaw. The equipment had never been used in a real-world crisis. Unit 1 was a ticking time bomb. ___ As the night wore on, the prime minister decided he had to go to Fukushima himself, at first light. His helicopter landed at 7:11 a.m. on March 12. Like everyone else in the entourage, Kan wore a blue-gray work uniform and had a dosimeter hanging around his neck. His aide, Shimomura, a former TV journalist, was assigned to chronicle the event. He started filming as the group boarded a minibus bound for the emergency crisis headquarters. It looked normal enough from the outside. Inside, though, was a madhouse. Dozens of workers raced back and forth, trying not to step on about 20 others either slumped to the floor or sleeping in blankets in the hallway. Shimomura turned off the camera. This scene would not reassure the nation, or the world. Escorted by TEPCO officials, Kan strode past men so preoccupied or tired that they didn't even acknowledge the presence of their country's leader. Kan, known for his short temper, fired questions at plant executives and pointed at diagrams of the reactors on a sheet of paper in front of them. He yelled at TEPCO Vice President Sakae Muto and plant chief Masao Yoshida, his onsite escorts, demanding to know why the venting and seawater injection were not happening. The discussions lasted only half an hour. At 8 a.m., Kan was on his way back to Tokyo. By then, TEPCO would later acknowledge, the core at Unit 1 had mostly melted, and units 2 and 3 were not far behind. At 2:30 p.m., workers burst into applause. Vapor was rising from the Unit 1 stack and containment vessel pressures fell
-- confirmation that the venting was working. But within half an hour, they ran out of fresh water. This was what TEPCO had dreaded. Fukushima Dai-ichi was built right next to the biggest source of water on the planet
-- the Pacific Ocean. Pumping water out of the ocean is an absolute last resort, however. The reactors would never be usable again. Yet again, TEPCO officials waffled. At 3:36 p.m., almost 24 hours to the minute after the second tsunami hit, the hydrogen inside Unit 1 combined with oxygen already there and exploded, in a fiery blast that blew off the roof and sent a plume of contaminated smoke and debris into the sky. The decision to use seawater was unavoidable. Blasts at units 2, 3 and 4 would follow in the coming days. TEPCO's primary task, and for months or even years, is still to repair the damage from the explosions. Japan's nuclear nightmare had begun.
[Associated
Press;
Copyright 2011 The Associated Press. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.
News | Sports | Business | Rural Review | Teaching & Learning | Home and Family | Tourism | Obituaries
Community |
Perspectives
|
Law & Courts |
Leisure Time
|
Spiritual Life |
Health & Fitness |
Teen Scene
Calendar
|
Letters to the Editor