Logan County Board to vote Sugar
Creek Wind Farm request for phased construction
Send a link to a friend
[March 18, 2019]
When the Logan County Board meets on Tuesday, March 19, they will be
voting on requests for changes for the Sugar Creek Wind Farm. That
project is expected to begin construction soon.
Planning and Zoning Chairman David Hepler said he will bring forward
three motions.
-
to
allow Sugar Creek to be completed in phases
-
to
allow nighttime construction activities unless prohibited by the
road use agreement
-
to
authorize Patrick Engineering to review the Decommissioning Plan
At the Logan County Planning and Zoning Committee meeting on
Wednesday, March 6, project representatives discussed the changes
they are seeking.
Logan County Zoning Officer Will D’Andrea said he has talked to the
developers about some of the requests, but the board must give them
the “go ahead” for these changes.
Yuri Attaro, project manager, talked about what changes they are
asking for some of the conditions. One condition is that they submit
design certificates once it has been determined what turbines will
be used for the project.
Attaro said these certificates are provided by a third-party
engineering firm, but there are issues with the design certificates
since one turbine model is still being designed.
There are two different turbine models for the project, the Vestas
110 and the Vestas 150. They have the design certificates for the
Vestas 110, which is an older model. However, the Vestas 150 is a
brand-new machine and the first prototype was just put up a few
months ago in Europe.
Attaro is asking the board to allow the issuance of foundation
building permits prior to the issuance of a tower permit. The
developers are looking to have the tower permits issued closer to
April 2020, and by that time, they will have the design certificates
in place. Attaro is requesting they be allowed to start some of the
construction in 2019 without having the certificates in place.
Kyle Barry, attorney for the project, said a similar category of
certificates is required under conditions numbers three and four
that professional engineers must sign off on and it may take a while
to get the certificates. He asked if they could proceed in phases.
Attaro said condition three requires that a professional engineer
licensed in the state of Illinois sign-off on tower and foundation
design certificates and they will have foundation design
certificates and are working to satisfy the tower design for the
newer one.
[to top of second column] |
D’Andrea said permitting is done in two phases starting with foundation only.
Normally he gets the certifications prior to issuing a foundation permit, but
the phasing schedule can still happen. D’Andrea said the only change is allowing
some construction without certification, but construction of towers will not
start without the certifications.
Committee member Chuck Ruben asked if the permit dollars would still come in
this fall and D’Andrea said yes.
The board will vote on whether to allow Sugar Creek to be completed in phases.
The second change Attaro requested was a waiver on the sunrise to sunset
condition for some filling work that will need to be done overnight.
D’Andrea asked how many concrete trucks would be needed and how long it would
take to pour foundations.
Attaro said pouring concrete will take about 16 hours and for safety reasons,
concrete pouring cannot be stopped once it is started.
Ruben said he has talked to several other board members and all are of the
opinion that nighttime construction other than roadwork be allowed, so they can
get in and get done.
Committee member Kevin Bateman said construction of the towers, blade placement,
hub placement, pouring concrete, and the switch station should be allowed at
night within reason.
Committee member Scott Schaffenacker said they have no way of enforcing it after
the fact.
The board will be voting whether to allow nighttime construction activities
unless prohibited by the road use agreement.
The last issue Attaro asked was about whether the decommissioning plan submitted
after being done by Westwood Engineering could be reviewed by Patrick
Engineering as a third party.
Bateman said Patrick Engineering did well with HillTopper’s plans and motioned
to use Patrick Engineering as the third party to look at the decommissioning
plans.
The board will vote on all three motions at Tuesday’s board meeting.
[Angela Reiners]
Past related articles:
Sugar Creek Wind Farm turbines will be located west of Lincoln, south of Route
10.
Liberty Power Moves Ahead with 202 MW Sugar Creek Wind Project
Sugar Creek Wind Farm project asks Logan County assistance in utilities easement
snag
Sugar Creek Wind Farm developers seek approval of changes and fewer turbines |